What is Percent Delay?
Percent Delay measures how much a task or project exceeded its allocated time as a percentage. This metric is essential in project management for tracking schedule performance, identifying bottlenecks, and improving future time estimates.
How to Calculate Percent Delay
The formula for calculating percent delay is:
[\text{Percent Delay} = \frac{\text{Actual Time} - \text{Allocated Time}}{\text{Allocated Time}} \times 100]
Where:
- Percent Delay is the percentage by which the actual time exceeded the allocated time
- Actual Time is the time actually taken to complete the task
- Allocated Time is the planned or budgeted time
Calculation Example
Suppose a project was allocated 10 days but actually took 13 days to complete.
Step 1: Identify the values:
- Actual Time: 13 days
- Allocated Time: 10 days
Step 2: Apply the formula:
[\text{Percent Delay} = \frac{13 - 10}{10} \times 100]
Step 3: Calculate:
[\text{Percent Delay} = \frac{3}{10} \times 100 = 30%]
The project experienced a 30% delay.
Interpretation Guide
| Percent Delay | Performance |
|---|---|
| < 0% | Ahead of schedule |
| 0% | On schedule |
| 1% - 10% | Minor delay |
| 11% - 25% | Moderate delay |
| > 25% | Significant delay |